Widener Memorial School

Louis A Bencardino Excavating
Widener Memorial School
Bencardino was awarded the Paving and Stormwater Management Project for the Widener Memorial School in Philadelphia. The project started is to be completed in two phases. Phase 1 started in early April 2019 and completed in middle of May 2019. Phase 2 started in early June 2019 and is scheduled to be completed by middle of August 2019. The project consists of constructing a new on-site storm system to control the stormwater from the entire parking area and driveways. The existing storm line was a combination line, which handled sanitary waste and storm runoff. With the construction of new storm lines, the on-site sanitary waste and storm runoff will be separate lines. In addition to the new storm system, Bencardino is resurfacing the parking lots and drive areas with new asphalt.