Success Stories


When Merck & Co. needed a utility tunnel, plus a total utility relocation in six months, start-to-finish, Bencardino worked with Bovis Lend Lease to get the work done. The job required excavation of 50,000 yards of dirt and 25,000 yards of rock, as well as substantial shoring to build a tunnel that was 25-feet deep and 40-feet wide. The biggest challenge for Bencardino was to keep the utilities in service the entire time. Not only were all utilities maintained and uninterrupted during the process, but Bencardino also finished the job ahead of schedule. (Testimonial…)


Shoemaker Construction called Bencardino in on a job for Princeton University, one that required excavation of 20,000 yards of earth, 10,000 of which was rock. The job required substantial shoring and lagging for a permanent, in-place shoring system. Because of Princeton's student population, there were also numerous safety concerns and regulations involved. Bencardino was able to comply with all rules and regulations, and work within specific means to get the job done right on-schedule. (Testimonial…)

Commerce Bank is a franchise that works on a very tight agenda, usually requiring work to be done in 10 weeks, start-to-finish. A Commerce job always requires demolition clearing and complete site work, including specialty items such as Belgian block curbing. Scheduling is critical, and the bank had problems with site contractors in the past. When Adams-Bickel brought Bencardino on to do the work, our guys showed up when they were supposed to. Bencardino was consistent, and we continue to be so -- getting the job done on time, every time. (Testimonial…)


Copyright ©2005 Bencardino Excavating, All Rights Reserved.

 

Back to our Home Page
Back to Last Page Visited